Strategic Systems Analysis: Task Report

Task Start End Duration Completed Dependencies Assigned Planned Start Start Variance Planned End End Variance
1) Planning 10/24/16 12/12/16 2mo 1d 100% 10/24/16 0h 12/12/16 0h
1.5) Interest Groups Brainstorming 11/22/16 12/12/16 3w 1d 4h 100% 1.4 11/22/16 0h 12/12/16 0h
2) Planning Completed 12/12/16 12/12/16 100% 1 12/12/16 0h 12/12/16 0h
3) First Round Reporting 11/21/16 12/14/16 1mo 1h 100% 11/21/16 0h 12/14/16 0h
3.2) LMG Update 11/28/16 11/30/16 2d 5h 100% 11/28/16 0h 11/30/16 0h
3.3) Library Council Update 12/9/16 12/14/16 4d 100% 3.2 12/9/16 0h 12/14/16 0h
4) Task Descriptions Round 1 12/14/16 6/16/17 6mo 3w 2d 4h 100% 12/14/16 0h 5/29/17 3w 2d 1h
4.1) Finish Analysis Task Descriptions 12/14/16 4/27/17 4mo 3w 2d 100% 12/14/16 0h 4/11/17 2w 1d 5h
4.2) 1st Task Descriptions Completed 4/27/17 4/27/17 100% 4.1 4/11/17 2w 1d 5h 4/11/17 2w 1d 5h
4.3) Write up TDs 1/16/17 5/30/17 5mo 1w 2d 3h 100% 3.3.2 1/13/17 1d 4h 5/9/17 3w 2d 1h
4.4) Revise Write ups based on Feedback with Leads (TD Review 1) 1/30/17 6/16/17 5mo 2w 1d 5h 100% 1/26/17 2d 2h 5/29/17 3w 2d 1h
5) Task Descriptions Round 1 Completed 6/16/17 6/16/17 100% 4.4 5/29/17 3w 2d 1h 5/29/17 3w 2d 1h
6) Task Descriptions Interest Group Review 1 (TD Review 2) 6/16/17 8/23/17 2mo 2w 2d 4h 100% 5/29/17 3w 2d 1h 8/2/17 3w 1h
6.1) Review all task descriptions by leads with interest groups 6/16/17 8/1/17 1mo 3w 4h 100% 5 5/29/17 3w 2d 1h 7/13/17 3w 1h
6.2) TD Review 2 Completed 8/1/17 8/1/17 100% 6.1 7/13/17 3w 1h 7/13/17 3w 1h
6.3) Task Descriptions Revisions 8/1/17 8/23/17 3w 2d 100% 6.1 7/13/17 3w 1h 8/2/17 3w 1h
7) Task Descriptions Group Review 1 Completed 8/23/17 8/23/17 100% 6, 6.3 8/2/17 3w 1h 8/2/17 3w 1h
8) Task Descriptions Feedback Across Groups 8/24/17 9/14/17 3w 1d 5h 100% 7 8/3/17 3w 1h 8/25/17 3w 1h
8.1) Review all task descriptions by leads across groups 8/24/17 9/14/17 3w 1d 5h 100% 8/3/17 3w 1h 8/25/17 3w 1h
9) Task Descriptions Feedback Round 2 Completed 9/14/17 9/14/17 100% 8.1 8/25/17 3w 1h 8/25/17 3w 1h
11) General Stakeholder feedback Period 9/14/17 10/12/17 1mo 2d 1h 100% 9 8/25/17 3w 1h 9/22/17 3w 1h
11.4) General Stakeholders Feedback Completed 10/12/17 10/12/17 100% 11.3 9/22/17 3w 1h 9/22/17 3w 1h
12) Task Descriptions Stakeholder feedback Period 10/12/17 11/15/17 1mo 1w 3d 45% 9, 11.3 9/22/17 3w 1h 11/6/17 1w 3d 1h
12.5) Task Descriptions Stakeholder feedback completed 11/15/17 11/15/17 0% 12.4 11/6/17 1w 3d 1h 11/6/17 1w 3d 1h
13) Gap Analysis 11/15/17 11/22/17 1w 1d 2h 100% 12.4 11/6/17 1w 3d 1h 11/13/17 1w 3d 1h
13.3) Gap Analysis Completed 11/15/17 11/15/17 100% 11/6/17 1w 3d 1h 11/6/17 1w 3d 1h
15) Final Report Completed 12/19/17 12/19/17 0% 14 12/8/17 1w 3d 1h 12/8/17 1w 3d 1h
16) Environmental Scan 6/1/17 7/31/17 2mo 1w 3d 3.875h 100% 6/1/17 0h 7/31/17 0h
17) Environmental Report Completed 7/31/17 7/31/17 100% 16 7/31/17 0h 7/31/17 0h

Exported 11/16/17